Florham Park Board of Education
Capital Projects
FY2019 Referendum Project Schedule
*Note: Majority of work completed during summer months of calendar year indicated*
CY 2020
Project # |
School |
Project Description |
Project Updates |
1
|
Briarwood |
Roof Replacement on original building |
Completed |
2 |
Briarwood |
Renovate Computer Lab to Gen. Ed. Classrooms |
Completed |
4 |
Briarwood |
Replace Lighting, Ceiling, Kalwall in Multi-purpose Room |
Completed |
5 |
Briarwood |
Replace Classroom ACM Flooring with VCT |
Completed |
8 |
Brooklake |
Replace Building Ceilings & Lighting |
Completed |
9 |
Brooklake |
Renovate Boy's and Girl's Bathrooms(4) |
Completed |
10 |
Brooklake |
Renovate Single Bathrooms Music Rooms(2) |
Completed |
12 |
Brooklake |
Replace Classroom ACM Flooring with VCT |
Completed |
13 |
Brooklake |
HVAC Instructional Areas/DDC Controls |
Completed |
14 |
Brooklake |
Replace Roof on Original Building |
Completed |
15 |
Brooklake |
Boiler Replacement to High Efficiency Boilers |
Completed |
18 |
Ridgedale |
Slate Roof Repairs and Repairs to Ridge and Valleys |
CY 2025 |
24 |
Ridgedale |
Replace Boilers with High Efficiency Boilers |
Completed |
CY 2021
Project # |
School |
Project Description |
Project Updates |
19 |
Ridgedale |
Renovate Bathrooms in Original Building(6) |
Completed |
20 |
Ridgedale |
Renovate Wellness Center/ Wood Shop/ Media Center to STEM Lab/ Learning Commons |
Completed |
21 |
Ridgedale |
Renovation Auditorium Seating, Lights, Audio |
Completed |
22 |
Ridgedale |
Replace Stage Air Conditioning Unit |
Completed |
23 |
Ridgedale |
HVAC Instructional Space in Original Building DDC Controls |
Completed |
26 |
Ridgedale |
Replace Original Building Ceiling/Lighting(LED) |
Completed |
CY 2022
Project # |
School |
Project Description |
Project Updates |
11 |
Brooklake |
Renovate Main Office/Principal/Nurse Safety |
Completed |
16 |
Brooklake |
Renovate Computer Lab to SGI(2) |
Completed |
17 |
Brooklake |
Renovate Media Center and Art Room to Learning Commons / STEAM Lab / SGI(2) |
Completed |
CY 2023
Project # |
School |
Project Description |
Project Updates |
6 |
Briarwood |
Replace Windows in Original Building |
Completed |
7 |
Briarwood |
Replace Ceilings/Lighting Building(LED)(Occupancy) |
Completed |
CY 2024
Project # |
School |
Project Description |
Project Updates |
3
|
Briarwood |
Renovate CST Area |
Completed
|
18 |
Ridgedale |
Slate Roof Repairs and Repairs to Ridge and Valleys |
CY 2025 |
25 |
Ridgedale |
Replace Emergency Generator with Larger Generator and/or Portable |
|
27 |
Ridgedale |
Mill & Repave Parking Lots, Access Drives, Sidewalks |
|
CY 2025
Project # |
School |
Project Description |
Project Updates |
18
|
Ridgedale |
Slate Roof Repairs and Repairs to Ridge and Valleys |
|